Work planned for week starting 11 October 2021
Below is a summary of the work planned for each week day.
Monday 4 October 2021
Set up traffic management (temporary traffic signals) from the bridge up to just before the junction with Market Street.
Start saw cutting for the new kerb line outside the Royal Hotel into Bridge Street.
Tuesday 5 October 2021
Continue with the work on Bridge Street.
Prepare for the new kerb line along Castle Street.
Wednesday 6 October 2021
Start to lay new kerbs on Bridge street.
Dig out along Castle Street ready for the new kerbs to be laid.
Thursday 7 October 2021
Continue with Castle Street kerb preparations.
Dig up the path along Bridge Street.
Friday 8 October 2021
Lay new kerbs along Castle Street.