Road surfacing programme 2023 to 2024

The programme for 2023 to 2024 includes £4 million of countywide works, which will include resurfacing of the carriageways and associated works (for example, sweeping and drainage). These may be subject to change following site assessments and dates are dependent on weather conditions and the availability of resources.

  • Aberwheeler: B5429 Aberwheeler to Llanelidan (sections) (resurfacing) - October 2023 to March 2024
  • Bodelwyddan: Ty Fry Road (resurfacing) - October 2023 to March 2024
  • Bryneglwys: A5104 east of village (resurfacing) - October 2023 to March 2024
  • Carrog: village to Rhewl (more of this road) (surfacing) - July to October 2023
  • Clawddnewydd: Derwen Hall (surface dressing) - June to August 2023
  • Corwen: A5437 leisure centre to Carrog (resurfacing) - October 2023 to March 2024
  • Corwen: Uwch y Dre, Cae Ffynnon, The Crescent, Hill Street (micro asphalt) - deferred until Spring 2024
  • Cyffylliog: Derwen Fawr (surfacing) - date to be confirmed
  • Denbigh: Karen Court, Llys Catrin (micro asphalt) - deferred until Spring 2024
  • Denbigh: Llys Thomas Jones (micro asphalt) - deferred until Spring 2024
  • Dyserth: B5119 Waterfalls road (resurfacing) - October 2023 to March 2024
  • Gellifor: Bodawen (micro asphalt) - deferred until Spring 2024
  • Prestatyn: Fforddlas (top part) (resurfacing) - October 2023 to March 2024
  • Rhuddlan: Bryn Afon, Ffynnon Cae Glas, Ffordd Cae Glas (micro asphalt) - deferred until Spring 2024
  • Rhyl: Clifton Park Road and part of Hadley Crescent (Micro Asphalt) - deferred until Spring 2024
  • Rhyl: Clwyd Avenue (micro asphalt) - deferred until Spring 2024
  • Rhyl: Kinard Drive (micro asphalt) - deferred until Spring 2024
  • St Asaph: A525 Tweedmill to Trefnant lights (surface dressing) - June to August 2023
  • St Asaph: Ashly Court (surfacing) - October 2023 to March 2024
  • St Asaph: Bryn Polyn (surfacing) - October 2023 to March 2024
  • St Asaph: Tan y Bryn, Pant Glas, Bryn Arthur (micro asphalt) - deferred until Spring 2024
  • Trefnant: Link road from Graig Road to A525 (resurfacing) - October 2023 to March 2024

Works completed

  • Clawddnewydd: B5105 east of village (resurfacing) - June to September 2023 - completed
  • Cwm: B5429 Cwm to Rhuallt (surface dressing) - June to August 2023 - completed
  • Cwm: Hiraddug Road (A55 end) (surfacing) - October 2023 to March 2024 - completed
  • Cynwyd: Ifor Williams to village centre (resurfacing) - June to September 2023 - completed
  • Efenechtyd: Tai Isa (surfacing) - completed
  • Eyarth: Eyarth to Rhydymeudwy (surfacing) - July to October 2023 - completed
  • Gellifor: Commins (surfacing) - completed
  • Llandegla: A525 to County boundary (surface dressing) - June to August 2023 - completed
  • Llanelidan: Llidiart y Sais / Merllyn (surfacing) - completed
  • Llanelidan: village to A494 (resurfacing) - July to October 2023 - completed
  • Llangollen: A542 Abbey Road (surface dressing) - June to August 2023 - completed
  • Llangollen: East Street (resurfacing) - October 2023 to March 2024 - completed
  • Llangollen: Parade Street (resurfacing) - October 2023 to March 2024 - completed
  • Meliden: Bryniau (resurfacing) - October 2023 to March 2024 - completed
  • Melin y Wig: Tan y Bwlch (surfacing) - July to October 2023 - completed
  • Prion: Bryn Rossa to Prion (surfacing) - October 2023 to March 2024 - completed
  • Rhyl: A548 Wellington Road and High Street (resurfacing) - June 2023 - completed
  • Rhyl: Church Street (resurfacing) - October 2023 to March 2024 - completed
  • Rhyl: Crescent road (2 sections) (resurfacing) - October 2023 to March 2024 - completed
  • Rhyl: Hammond Court (surface dressing) June to August 2023 - completed
  • Saron: Saron Hill (surface dressing) - June to August 2023 - completed
  • St Asaph: Cefn Road (half in 2023/24) (surfacing) - October 2023 to March 2024 - completed
  • Trefnant: A525 Trefnant traffic lights (resurfacing) - October 2023 to March 2024 - completed