Levelling Up Fund Round 2: Programme Delivery Plan

Funded by UK Government logo

Information about the Levelling Up Fund Round 2 project's programme delivery plans.

Delivery plan key milestones

All delivery plan milestones are provisional and are based on best information at this stage in the project’s development. 

This information will be updated if information changes.

Select one of the following projects to view it's delivery plan key milestones:

St Peter's Square
St Peter’s Square Programme Delivery Plan
Key Milestone Date 
Consultation and engagement April/May 2024
Detailed designs available March/April 2024
Traffic Regulation Order submitted October/November 2024
Procurement start December 2024
Construction start September 2025
Handover February 2026
St Peter's Church and Cloisters
St Peter's Church and Cloisters Programme Delivery Plan
Key Milestone Date 
Procurement start June 2024
Construction start September 2024
Construction Finish / Handover August/September 2025
Ruthin Clock Tower
Ruthin Clock Tower Programme Delivery Plan
Key Milestone Date 
Procurement start April 2024
Consultation and engagement April/May 2024
Construction start August 2024
Construction finish / Handover October/November 2024
Ruthin Gaol/46 Clwyd Street
Ruthin Gaol/46 Clwyd Street Programme Delivery Plan
Key Milestone Date 
Detailed designs available March/April 2024
Planning application submitted May/June 2024
Procurement start August/September 2024
Construction start October/November 2024
Construction finish / Handover February/March 2025
Ruthin Nantclwyd y Dre
Ruthin Nantclwyd y Dre Programme Delivery Plan
Key Milestone Date 
Planning application submitted May/June 2024
Procurement Start July/August 24
Construction start November 2024
Construction finish / Handover May/June 2025
Ruthin Cae Ddol
Ruthin Cae Ddol Programme Delivery Plan
Key Milestone Date 
Consultation and engagement April/May 2024
Planning Application Submitted October 2024
Construction Start September 2025
Construction finish / Handover February 2026
Moel Famau Facilities and Cycle Paths
Moel Famau Facilities and Cycle Paths Programme Delivery Plan
Key Milestone Date 
Consultation and engagement February/March 2024
Planning application submitted April/June 2024
Procurement start August/September 2024
Construction start December 2024
Construction finish / Handover June 2025
Loggerheads Building and External
Loggerheads Building and External Programme Delivery Plan
Key Milestone Date 
Consultation and engagement February/March 2024
Planning Application and FRAP Consent App Submitted April 2024/September 2024
Procurement start August/September 2024
Construction start December 2024
Construction finish / Handover June 2025
Bryneglwys School - Community Hub
Bryneglwys School - Community Hub Programme Delivery Plan
Key Milestone Date 
Procurement start May 2024
Construction start July 2024
Handover November 2024
Gwyddelwern - Community Hub
Gwyddelwern - Community Hub Programme Delivery Plan
Key Milestone Date 
Pre-planning consultation May/June 2024
Planning application Submitted July/August 2024
SAB application submission July/August 2024
Procurement start January 2025
Construction start May 2025
Construction finish / Handover March 2026