Levelling Up Fund Round 2: Programme Delivery Plan
Information about the Levelling Up Fund Round 2 project's programme delivery plans.
Delivery plan key milestones
All delivery plan milestones are provisional and are based on best information at this stage in the project’s development.
This information will be updated if information changes.
Select one of the following projects to view it's delivery plan key milestones:
St Peter's Square
St Peter’s Square Programme Delivery Plan
Key Milestone |
Date |
Consultation and engagement |
March/April/May 2024 |
Detailed designs available |
March/April 2024 |
Traffic Regulation Order submitted |
September/October/November 2024 |
Procurement start |
December 2024 |
Construction start |
September 2025 |
Handover |
February 2026 |
St Peter's Church and Cloisters
St Peter's Church and Cloisters Programme Delivery Plan
Key Milestone |
Date |
Procurement start |
February 2024 |
Construction start |
April 2024 |
Construction Finish / Handover |
March/April 2025 |
Ruthin Clock Tower
Ruthin Clock Tower Programme Delivery Plan
Key Milestone |
Date |
Procurement start |
February/March 2024 |
Consultation and engagement |
March/April/May 2024 |
Construction start |
June 2024 |
Construction finish / Handover |
October/November 24 |
Ruthin Gaol/46 Clwyd Street
Ruthin Gaol/46 Clwyd Street Programme Delivery Plan
Key Milestone |
Date |
Detailed designs available |
March/April 2024 |
Planning application submitted |
March/April 2024 |
Procurement start |
August/September 2024 |
Construction start |
November 2024 |
Construction finish / Handover |
May/June 2025 |
Ruthin Nantclwyd y Dre
Ruthin Nantclwyd y Dre Programme Delivery Plan
Key Milestone |
Date |
Planning application submitted |
March/April 2024 |
Procurement Start |
July / August 24 |
Construction start |
November 2024 |
Construction finish / Handover |
July/August 2025 |
Ruthin Cae Ddol
Ruthin Cae Ddol Programme Delivery Plan
Key Milestone |
Date |
Consultation and engagement |
March/April/May 2024 |
Planning Application Submitted |
October 2024 |
Construction Start |
September 2025 |
Construction finish / Handover |
February 2026 |
Moel Famau Facilities and Cycle Paths
Moel Famau Facilities and Cycle Paths Programme Delivery Plan
Key Milestone |
Date |
Consultation and engagement |
February/March 2024 |
Planning application submitted |
April/June 2024 |
Procurement start |
August/September 2024 |
Construction start |
December 2024 |
Construction finish / Handover |
June 2025 |
Loggerheads Building and External
Loggerheads Building and External Programme Delivery Plan
Key Milestone |
Date |
Consultation and engagement |
February/March 2024 |
Planning Application and FRAP Consent App Submitted |
April 2024/September 2024 |
Procurement start |
August/September 2024 |
Construction start |
December 2024 |
Construction finish / Handover |
June 2025 |
Bryneglwys School - Community Hub
Bryneglwys School - Community Hub Programme Delivery Plan
Key Milestone |
Date |
Procurement start |
February 2024 |
Construction start |
April 2024 |
Handover |
September 2024 |
Gwyddelwern - Community Hub
Gwyddelwern - Community Hub Programme Delivery Plan
Key Milestone |
Date |
Pre-planning consultation |
March 2024 |
Planning application Submitted |
April/June 2024 |
SAB application submission |
April/July 2024 |
Procurement start |
November 2024 |
Construction start |
March 2025 |
Construction finish / Handover |
December 2025 |